Hydel Projects

Particulars of running Hydro-power stations under Hydel HQ

Name of the Projects Installed Capacity
Rammam Hydel Project 51 MW
(4 x 12.75 MW)
Teesta Canal Fall Hydel Project (PS-I, PS-II & PS-III) 67.5.MW
(3 PS x 3 Units x 7.5 MW)
Jaldhaka HEP 44 MW
Stage – I (4 x 9 MW) + Stage – II (2 x 4 MW)
Sidrapong HEP 600 KW (3 x 200 KW)
Little Rangit HEP 2 MW (2 x 1.0 MW)
Rinchington HEP 2 MW (2 x 1.0 MW)
Fazi HEP 1.2 MW (1 x 1.2 MW)
Mungpo-Kalikhola HEP 3 MW (3 x 1.0 MW)


GENERATION FROM THE HYDRO POWER STATIONS DURING 2015-16:



Sl No. Name of the Power Station Generation figure for 2015-16 Target fixed by CEA for 2016-17
Target fixed by CEA Achieved
1 Rammam Hydel Project (Stage-II) [4x12.75 MW] 238 MU 253.9751 MU 238 MU
2 Jaldhaka Hydel Project (Stage-I)[4x9 MW) 141 MU 137.688 MU 158MU
3 Jaldhaka Hydel Project (Stage-II)[2x4 MW] No target fixed by CEA being the Station Capacity below 25 MW. 35.763 MU -----
4 Teesta Canal Fall Hydel project[3x3x7.5 MW] No target fixed by CEA being the Station Capacity below 25 MW 79.9891MU -----
5 Small Hydel Projects (SHP)      
  Mungpoo Kali Khola SHP(3x1 MW) No target fixed by CEA being the Station Capacity below 25 MW 7.299 MU  
  Rinchington SHP (2x1 MW) 1.2933 MU  
  Little Rangit Hydel SHP(2x1 MW) 8.280 MU  
  Fazi SHP (1x1200 KW) 1.365 MU  
  Sidrapong SHP (2 x 0.2 MW) 0.1155 MU  
  Total Generation   525.768 MU  
Rammam Intermediate HEP (12 MW) in Dist. Darjeeling is under implementation

Hydel Projects

Particulars of running Hydro-power stations under Hydel HQ

Name of the Projects
Rammam Hydel Project
Installed Capacity
51 MW
(4 x 12.75 MW)
Name of the Projects
Teesta Canal Fall Hydel Project (PS-I, PS-II & PS-III)
Installed Capacity
67.5.MW
(3 PS x 3 Units x 7.5 MW)
Name of the Projects
Sidrapong HEP
Installed Capacity
600 KW (3 x 200 KW)
Name of the Projects
Little Rangit HEP
Installed Capacity
2 MW (2 x 1.0 MW)
Name of the Projects
Rinchington HEP
Installed Capacity
2 MW (2 x 1.0 MW)
Name of the Projects
Fazi HEP
Installed Capacity
1.2 MW (1 x 1.2 MW)
Name of the Projects
Mungpo-Kalikhola HEP
Installed Capacity
3 MW (3 x 1.0 MW)


GENERATION FROM THE HYDRO POWER STATIONS DURING 2015-16:



Sl No.
1
Name of the Power Station
Rammam Hydel Project (Stage-II) [4x12.75 MW]
Target fixed by CEA
238 MU
Achieved
253.9751 MU
Target fixed by CEA for 2016-17
238 MU
Sl No.
2
Name of the Power Station
Jaldhaka Hydel Project (Stage-I)[4x9 MW)
Target fixed by CEA
141 MU
Achieved
137.688 MU
Target fixed by CEA for 2016-17
158MU
Sl No.
3
Name of the Power Station
Jaldhaka Hydel Project (Stage-II)[2x4 MW]
Target fixed by CEA
No target fixed by CEA being the Station Capacity below 25 MW
Achieved
35.763 MU
Target fixed by CEA for 2016-17
-----
Sl No.
4
Name of the Power Station
Teesta Canal Fall Hydel project[3x3x7.5 MW]
Target fixed by CEA
No target fixed by CEA being the Station Capacity below 25 MW
Achieved
79.9891MU
Target fixed by CEA for 2016-17
-----
Sl No.
5
Name of the Power Station
Small Hydel Projects (SHP)
Target fixed by CEA
 
Achieved
 
Target fixed by CEA for 2016-17
 
Sl No.
 
Name of the Power Station
Mungpoo Kali Khola SHP(3x1 MW)
Target fixed by CEA
No target fixed by CEA being the Station Capacity below 25 MW
Achieved
7.299 MU
Target fixed by CEA for 2016-17
 
Sl No.
 
Name of the Power Station
Rinchington SHP (2x1 MW)
Target fixed by CEA
No target fixed by CEA being the Station Capacity below 25 MW
Achieved
1.2933 MU
Target fixed by CEA for 2016-17
 
Sl No.
 
Name of the Power Station
Little Rangit Hydel SHP(2x1 MW)
Target fixed by CEA
No target fixed by CEA being the Station Capacity below 25 MW
Achieved
8.280 MU
Target fixed by CEA for 2016-17
 
Sl No.
 
Name of the Power Station
Fazi SHP (1x1200 KW)
Target fixed by CEA
No target fixed by CEA being the Station Capacity below 25 MW
Achieved
1.365 MU
Target fixed by CEA for 2016-17
 
Sl No.
 
Name of the Power Station
Sidrapong SHP (2 x 0.2 MW)
Target fixed by CEA
No target fixed by CEA being the Station Capacity below 25 MW
Achieved
0.1155 MU
Target fixed by CEA for 2016-17
 
Sl No.
 
Name of the Power Station
Total Generation
Target fixed by CEA
No target fixed by CEA being the Station Capacity below 25 MW
Achieved
525.768 MU
Target fixed by CEA for 2016-17
 


Rammam Intermediate HEP (12 MW) in Dist. Darjeeling is under implementation