Sl No. | Name of the project | Project cost (Rs. in Cr.) | Source of Funding | Progress upto 2015-16 | Plan for 2016-17 | ||
---|---|---|---|---|---|---|---|
Physical (in Nos) |
Financial (Rs. in Cr.) |
Physical (in Nos) |
Financial (Rs. in Cr.) |
||||
A. | Upgradation and strengthening of sub-transmission and distribution system in 68 towns | 808.78 | 25% from PFC,the nodal agency & 75% from REC as counter part funding | 46 (Completed) |
347.08 | 22 (6 nos towns completed, 11 nos to be completed by March'17. Balance 5 nos to be completed by March'18) |
461.70 |
Sl No. | Name of the project | Project cost (Rs. in Cr.) | Source of Funding | Progress upto 2015-16 | Plan for 2016-17 | ||
---|---|---|---|---|---|---|---|
Physical (in %) |
Financial (Rs. in Cr.) |
Physical (in %) |
Financial (Rs. in Cr.) |
||||
A. | Upgradation, strengthening of sub-transmission & distribution system and conversion of overhead to underground cabling in Bolpur town | 90.75 | 10% own fund and 90% from GOI through REC | 80% | 52.00 | 20% (Target of completion: Dec, 16) |
38.75 |
B. | Upgradation, strengthening of sub-transmission & distribution system and conversion of overhead to underground cabling in Nabadwip town | ||||||
C. | Augmentation of 33/11 KV sub-station | 114.55 | 70% | 55.60 | 30% (Target of completion: Jan, 17) |
58.95 | |
D. | Replacement of 33 & 11 KV OCB by VCB |